• An Giang
  • Binh Duong
  • Binh Phuoc
  • Binh Thuan
  • Binh Dinh
  • Bac Lieu
  • Bac Giang
  • Bac Kan
  • Bac Ninh
  • Ben Tre
  • Cao Bang
  • Ca Mau
  • Can Tho
  • Dien Bien
  • Da Nang
  • Da Lat
  • Dak Lak
  • Dak Nong
  • Dong Nai
  • Dong Thap
  • Gia Lai
  • Ha Noi
  • Ho Chi Minh
  • Ha Giang
  • Ha Nam
  • Ha Tinh
  • Hoa Binh
  • Hung Yen
  • Hai Duong
  • Hai Phong
  • Hau Giang
  • Khanh Hoa
  • Kien Giang
  • Kon Tum
  • Lai Chau
  • Long An
  • Lao Cai
  • Lam Dong
  • Lang Son
  • Nam Dinh
  • Nghe An
  • Ninh Binh
  • Ninh Thuan
  • Phu Tho
  • Phu Yen
  • Quang Binh
  • Quang Nam
  • Quang Ngai
  • Quang Ninh
  • Quang Tri
  • Soc Trang
  • Son La
  • Thanh Hoa
  • Thai Binh
  • Thai Nguyen
  • Thua Thien Hue
  • Tien Giang
  • Tra Vinh
  • Tuyen Quang
  • Tay Ninh
  • Vinh Long
  • Vinh Phuc
  • Vung Tau
  • Yen Bai

Gov’t seeks ways boost disbursement of public investment

VGP – Prime Minister Nguyen Xuan Phuc presides over the national video-conference to seek solutions to slow disbursement of public investment.

September 26, 2019 10:13 AM GMT+7

Prime Minister Nguyen Xuan Phuc. Photo: VGP

Public investment accounts for 10.7% of GDP and 32% of total investment capital in 2019, according to Prime Minister Phuc.

Slow disbursement could hinder economic growth, undermine trust of investors and  donors, cause huge wastefulness, and increase investment costs, the Government chief frankly pointed out.

Disbursement varies from ministry to ministry and locality to locality, in which many ministries and localities have extremely low rate, from 10%-15% in the first nine months, he said.

Only seven ministries, agencies and 14 localities disbursed above 70% of capital, Phuc added.

According to the Ministry of Planning and Investment, obstacles leading to low disbursement rates include current regulations on public investment.

Many ministries, agencies and localities are still confused in application of new provisions of the Laws on land, construction, bidding, and environmental protection.

Meanwhile, it takes a long time for site clearance, approval of work designs and estimated amount of investment capital, and selection of contractors.

In addition, allocation of capital has not met the real progress of investment projects, the ministry reported.

ODA projects, there have been numerous shortcomings in project preparations, leading to low readiness, said the ministry./.

By Huong Giang